In short

A brief for a measured building survey says what the survey is for, what it covers, how accurate it must be, which drawings and files you need, and which grid and height datum to use. The usual UK reference is the RICS standard Measured surveys of land, buildings and utilities. The checklist below is ready to copy.

By Connor Milton MCIAT, Chartered Architectural Technologist Published Last reviewed 9 minute read

Existing front elevation of a Victorian townhouse at 1:50, drawn from a laser scan Open the full size sheet in a new tab
E01 Front elevation 1:50 Full size

What goes in a measured survey brief?

Six things: the purpose, the extent, the accuracy, the drawings and their detail, the grid and datum, and the files you want delivered. A brief that covers them lets every provider price the same measured building survey, and lets you check what arrives against what you asked for.

The Survey Association (now the Geospatial Survey Association) has a client guide to survey specification for architectural services. This guide for architects says the scope should be set at tender stage and should include the survey boundary, the level and accuracy of detail, the coordinate and level datum and the key deliverables. It adds that talking the requirements through with the provider, including why the survey is needed, helps them advise.

The usual UK reference for the detail is the RICS document Measured surveys of land, buildings and utilities (3rd edition). RICS reissued it in December 2023 as a professional standard. It sets out, item by item, what a client can specify.

Why start with the purpose?

Because the purpose decides the rest. The RICS document says the first question is the purpose of the survey. The Survey Association’s guide to measured building surveys warns that a survey prepared for one purpose is not necessarily accurate or detailed enough for another. An outline plan for a lettable area may be surveyed to a lower accuracy than one an architect will use to design structural alterations.

So write down the work the drawings will support: an extension, a change of use, a fit out, a planning or building warrant application, a model for a design team. For the drawings an application normally needs, see our guide to existing drawings for planning and building warrant.

How do you specify accuracy?

With one default RICS accuracy band for the job, then a list of any features to be surveyed at a different band or not surveyed at all. That is how the RICS specification for measured building surveys is set out. RICS notes that features at bands B and C generally involve additional work and may cost more, so ask for a closer band only where the design needs it.

The band, not the drawing scale, is what you specify. RICS prints the old plot scale beside each band only as a guide for readers of its earlier editions: band D sits beside 1:50 and band E beside 1:100. Our guide to measured survey accuracy bands explains the bands and the confidence levels they are stated at.

Which drawings, and how much detail?

List each output you need. The RICS specification lets the client tick floor plans, a roof plan, reflected ceiling plans, cross sections, elevations, 3D models, BIM, registered point clouds, IPMS areas, ASCII data and a survey report.

Then say what each drawing must show. The RICS feature tables for measured building surveys start with the structure: walls, doors, windows, floors, ceilings, beams, columns and stairs. Internal roof and ceiling structure and under-floor details are surveyed only if the client selects them. The Survey Association’s guide to measured building surveys adds that the scale decides how much detail is shown, and that detail beyond the standard should be specified at the point of tendering. Our guide to what a measured building survey is gives its examples.

Mark your section lines on a plan. The guide for architects says the location of each section should be defined before the capture on site is complete.

Connected, semi-connected or unconnected?

The Survey Association’s guide to measured building surveys describes three types, and the type you ask for decides how the building is measured:

  • Connected. All floors are related to one survey control framework. The guide says this is usually asked for when major structural changes are proposed.
  • Semi-connected. One floor, normally the ground floor, is controlled, and the other floors are matched by assuming that common features are vertical.
  • Unconnected. Simple methods that do not let one part of the survey be related to another, traditionally used for lettable area plans.

Say which one you need in the brief. If several floors will be altered, or a model will tie them together, the difference matters.

Which grid and height datum?

Name both. RICS says all surveys shall be connected to a local or national grid, and gives the client a choice of height datum. It recommends relating every survey to the national height datum.

ChoiceOptionsWhat to know
Plan gridAn arbitrary grid, a local site grid, or the Ordnance Survey National GridNational Grid coordinates are reduced to mean sea level and use a projection scale factor, so distances taken from them differ from distances measured on the ground. The difference matters most on large or high sites
Height datumAn arbitrary datum, a site datum, or Ordnance Datum NewlynThe Survey Association’s guide says Ordnance Survey bench marks are no longer maintained and GNSS is now the standard way to give heights above mean sea level
Scottish islandsOrkney, Shetland and the Outer HebridesOrdnance Survey says heights there are related to local vertical datums, not to Ordnance Datum Newlyn

The table draws on the RICS document, The Survey Association’s guide for architects and Ordnance Survey’s guide to coordinate systems. If the job must fit an earlier survey or a site grid that the owner controls, send the details with the brief.

Which file formats should you ask for?

Name them. RICS sets no default format, because there is no settled convention, so the client specifies the formats or the provider confirms what it proposes. RICS recommends a standard exchange format as well as the format your own software uses, because software versions change. Its suggestions include DXF for CAD and LAS or E57 for point clouds.

The guide for architects says to give the exact format, any layering convention and the software version, so that costly conversions are avoided. It also says many survey firms keep the raw point cloud and supply only the deliverable asked for. If you want it, specify it: it may be charged for. For a point cloud, RICS suggests asking for spurious data from moving objects (people, vehicles, reflections) to be cleaned out, and for a generic format that will serve as an archive. Our guide to using a point cloud in AutoCAD or a browser covers what to do with one when it arrives.

What site information should the brief give?

Enough for the provider to plan the visit. RICS recommends that the client supplies a plan of the survey extent in PDF and in its source CAD format. Its specification also has places for the site contact, access arrangements such as keys and permits, constraints such as working hours, and existing survey information.

Tell the provider about hazards you know of. RICS recommends that the client gives notice of known hazards, such as asbestos or confined spaces, before the provider writes its risk assessment.

Agree what happens to hidden areas. Under the RICS specification the provider is not responsible for detail hidden by furniture, coverings, stacked materials, poor lighting or lack of access, unless clearance in advance was agreed and completed. Say which rooms will be cleared, and by whom.

Measured survey brief checklist

Copy the list into your brief and fill in each line. Leave out what does not apply.

The job

  1. Purpose. The work the survey will support, and who will use the drawings or model.
  2. Address and extent. The building, the floors, rooms and external areas to be surveyed, with a marked-up plan in PDF and CAD.
  3. Contacts. The client contact and the site contact.
  4. Access. Keys, permits, inductions, working hours and occupied areas.
  5. Known hazards. For example asbestos or confined spaces.
  6. Hidden areas. Rooms with furniture or stored goods, and who will clear them before the visit.
  7. Existing information. Earlier drawings or surveys you can share.
  8. Dates. When you need the drawings or model.

Accuracy and survey type

  1. Default accuracy band. For example RICS band D.
  2. Exceptions. Features at a different band, and features not to be surveyed.
  3. Survey type. Connected, semi-connected or unconnected.

Drawings and detail

  1. Outputs. Floor plans, roof plan, reflected ceiling plans, elevations, sections, a 3D model or a point cloud.
  2. Scales. The scale of each drawing.
  3. Detail beyond the standard. For example cornice profiles, internal roof and ceiling structure, under-floor details.
  4. Section lines. Marked on a plan before the survey.

Grid, datum and files

  1. Plan grid. Arbitrary, a local site grid or the Ordnance Survey National Grid.
  2. Height datum. Arbitrary, a site datum or Ordnance Datum Newlyn.
  3. CAD standard. Your layering convention, title block and template, the file format and the software version.
  4. Exchange formats. For example DXF for drawings and E57 for the point cloud, alongside your own formats.
  5. Point cloud. Whether you want it, cleaned of moving objects, and in which format.
  6. Model. For a Revit model: the elements to be modelled, your template and your BIM requirements.
  7. Data after delivery. How long the provider keeps the site data, or a request to receive it.

What a brief cannot fix

A laser scanner measures only what it can see. The Survey Association’s laser scanning guide says it cannot measure through, behind, around or underneath objects, so a crowded room or a closed void limits the record whatever the brief says. The same guide says distance, the angle to a surface and the surface finish all affect accuracy, and that laser scanning is not always the right tool for every project.

A band is a requirement for the finished survey, checked against the survey control. It is not a scanner’s rating, and naming a tight band does not make a survey fit for a purpose the brief did not state.

For a Revit model, our guide to scan to BIM LOD explains what the levels of development mean for an existing building. For a listed building, our guide to measured surveys of listed buildings in Scotland covers what the drawings need to show.

How Kanna Spatial does it

Kanna Spatial is a reality capture studio in Glasgow. We take the RICS document as the reference for your brief.

  • Accuracy. Tolerance is agreed at quote stage to suit the scale and purpose of the drawings. If your brief names an RICS accuracy band, include it when you ask for a quote, and we will confirm whether and how we can meet it.
  • Drawings. Drawings follow your CAD layer standard or Revit template, on sheets at 1:50 or 1:100 in DWG and PDF.
  • Models. Send your BIM execution plan and information requirements at the start and we will work within them.
  • Site control. Site control comes from you or your surveyor, and we tie the scan into it.
  • Point cloud. On request, the point cloud is supplied alongside the drawings, in E57 or Autodesk ReCap format.
  • Checks. Every drawing is checked before issue.

The West End townhouse case study shows a finished set of drawings. Every job is quoted at a fixed price before we attend, usually the same working day. Send us your brief with the address.

Questions

Can a brief name the RICS standard if the provider is not an RICS member?

Yes. RICS wrote it for survey knowledgeable clients who specify their own surveys, as well as for surveyors acting as advisers, and RICS members must comply with it. Name the document, or one of its accuracy bands, and ask the provider to confirm in writing how it will meet them.

Does a Revit model need a different brief?

It needs more in it. The Survey Association's guide for architects says a model of an existing building shows the correct geometry but not, for example, the make-up of a wall, and that scoping one needs careful thought. Say which elements are modelled and send your template. Our scan to BIM page covers what a model of an existing building holds.

Will the provider keep the scan data?

Not necessarily. The Survey Association's guide for architects says survey firms tend not to keep site data indefinitely, so if you may need it later, list it as a deliverable or set a period for it to stay available.

Sources

6
  1. Measured surveys of land, buildings and utilities, 3rd edition (PDF)RICS. Read
  2. Client guide to measured building surveys, Issue 4The Survey Association (now the Geospatial Survey Association). Read
  3. Client guide to survey specification for the provision of architectural services, Issue 1The Survey Association (now the Geospatial Survey Association). Read
  4. Client guide to terrestrial laser scanning, Issue 5The Survey Association (now the Geospatial Survey Association). Read
  5. Ordnance Survey coordinate systemsOrdnance Survey. Read
  6. National Geoid Model OSGM15Ordnance Survey. Read

Proof

Projects we can show you

All case studies

Get a price

Get a fixed price, usually the same working day

Send the address and what you need. No call needed: we reply with a price and a survey date.

What happens next

  1. 01We reply with a fixed price, usually the same working day.
  2. 02We agree a survey date.
  3. 03You receive everything in your client portal.

Prefer email? studio@kannaspatial.co.uk

What do you need?
Get a fixed price Email