Existing drawings for planning and building warrant in Scotland
In short
A planning application normally needs a location plan and existing and proposed plans and elevations at 1:50 or 1:100. A building warrant needs plans, sections and elevations, preferably at 1:50, with enough on the existing building to show the work does not harm it. Measured building surveys in Scotland produce that existing set.
By Connor Milton MCIAT, Chartered Architectural TechnologistPublished Last reviewed Last changed 7 minute read
Most projects on an existing building in Scotland start with drawings of the building as it is now. Planning officers, conservation officers and building standards verifiers compare what you propose against what exists, so the existing drawings are the base for everything else. Scotland runs separate processes for the look and use of the work and for how it is built, and each has its own application.
Planning permission covers the development itself, such as an extension, a change of use or new windows. The council, as planning authority, normally decides it. Listed building consent sits alongside it for listed buildings, and is also normally decided by the council. The Scottish Government’s current guidance on planning procedure is Planning Circular 3/2022, which replaced Circular 3/2013.
A building warrant deals with how the work is built. It is granted by a verifier, and at present the council’s building standards service is the verifier: the 32 Scottish councils are the only bodies appointed, each for its own area. Some projects need both planning permission and a warrant.
Both kinds of application can be made through eDevelopment.scot, the national portal run by the Scottish Government with the local and planning authorities: ePlanning for planning applications and eBuildingStandards for building warrants. For work to an existing building, each normally needs existing and proposed drawings, and one measured building survey can feed both.
What existing drawings does a planning application need?
The law asks for less than people expect. Regulation 9 of the 2013 development management regulations asks for a plan that identifies the land and its surroundings, and such other plans and drawings as are necessary to describe the development. It sets no scales. The scales come from guidance: Annex D of Circular 3/2022, which says its list is not a statutory requirement, and the national validation guidance from Heads of Planning Scotland.
Drawing
Usual scale
Where the scale comes from
Location plan
1:1250 or 1:2500
Heads of Planning Scotland guidance
Site or block plan
1:100, 1:200 or 1:500
Heads of Planning Scotland guidance
Existing floor plans
1:50 or 1:100
Circular 3/2022 Annex D, and Heads of Planning Scotland guidance
Existing elevations
1:50 or 1:100
Circular 3/2022 Annex D, and Heads of Planning Scotland guidance
Existing sections, where needed
1:50 or 1:100
Circular 3/2022 Annex D, and Heads of Planning Scotland guidance
Existing roof plan
1:50 or 1:100
Circular 3/2022 Annex D, and Heads of Planning Scotland guidance
Requirements vary by council and by application, so check your council’s validation checklist before you submit. The Circular says not every drawing is needed in every case, and that councils may publish their own guidance.
The Heads of Planning Scotland guidance says existing elevations should be detailed enough to give a true representation of the building as it stands, with the existing finishes, a scale bar and written heights to the eaves and the ridge. It also says the drawings in an application are cross-referenced with each other when the council validates it. Proposed drawings are produced on the same base as the existing ones, so if the existing drawings are wrong, the proposals inherit every error.
For listed buildings and conservation areas, the existing drawings need to record the building’s features faithfully: mouldings, string courses, chimney heads, window patterns and roof coverings. The council’s conservation officer will normally want to see them drawn, not described. Listed building consent is normally decided by the council, and the council must consult Historic Environment Scotland before deciding an application for works to a category A or B listed building or to demolish a listed building.
What existing drawings does a building warrant need?
The law on warrant drawings is Schedule 2 to the Building (Procedure) (Scotland) Regulations 2004. For an alteration it asks for plans, sections and elevations only so far as necessary to show that the work will meet the building regulations, at whatever scale the verifier requires. The current Building Standards Procedural Handbook (third edition, version 1.9, published by the Scottish Government on 25 March 2026 as advice and guidance) suggests these scales:
Drawing
Suggested scale
Where the scale comes from
Plans, sections and elevations
Not less than 1:100, with 1:50 preferred
Procedural Handbook, paragraph 3.3.18
Block plan
Not less than 1:1250, with 1:500 preferred
Procedural Handbook, paragraph 3.3.18
Location plan, where the block plan does not identify the site
Not less than 1:2500, with 1:1250 preferred
Procedural Handbook, paragraph 3.3.18
For an alteration or an extension, the Handbook says enough information on the existing building must be provided to show that it is not adversely affected. Its example is a building being subdivided, where the means of escape in the remaining part may need to be shown. The existing heights, stairs and floor levels are what the proposed structure, fire and access details are drawn against, so if they are wrong, the details drawn over them are wrong too.
If key information is missing, the Handbook says the verifier may accept the application on condition that it is supplied within 42 days.
Why are existing drawings the part that goes wrong?
Existing drawings are sometimes produced quickly, from a walk-round with a tape measure and a laser measure, by whoever is designing the scheme. That can work for a simple modern box. It works less well for the buildings many Scottish projects involve: sandstone tenements with bay windows and split-level closes, Victorian villas extended three times, Georgian townhouses in Edinburgh’s New Town, farm steadings that have never been square.
Faults to watch for:
Walls drawn parallel that are not, so the extension does not fit
Floor-to-ceiling heights taken in one room and applied to all
Roof structure guessed from the outside
Level changes between rooms missed
Elevations reconstructed from photographs, with windows in the wrong place
Each of these can show up either in the application, as a query, or on site, as a variation, a redesign and a delay.
How does a laser-scanned measured survey help?
A measured building survey drawn from a laser scan starts from a measured record of the building rather than a sketch. One site visit can combine a laser scan, an interior capture and drone photographs. The existing plans, elevations and sections are drawn from that record at the scales the application needs, and supplied in DWG and PDF so the designer draws the proposals straight over them.
Because the drawings come from the scan, they carry the building’s real geometry: the out-of-square rooms, the true ceiling heights, the fall across a floor and the roof as it sits. That is what the planning officer and the verifier compare your proposals against. For listed buildings the scan is also a record of the historic fabric, captured without touching it.
What should you ask for?
When you commission the survey, tell whoever is quoting:
What the drawings are for. “Existing drawings for a householder planning application and building warrant” is enough to scope the right set.
Which drawings and scales your council’s validation checklist or guidance asks for.
Whether the building is listed or in a conservation area, so heritage detail is drawn to the right level.
Your CAD standards (layers and title block), so the set drops straight into the proposed drawings.
That you want the point cloud too, as it answers questions during design without another visit.
This guide covers existing drawings. It does not cover the proposed drawings, the other documents an application may need (forms, certificates, statements and fees), or the technical standards a warrant is assessed against. It gives what national guidance normally asks for. Your council can ask for more, and the rules change: check the current guidance and your council’s checklist before you submit. A measured building survey is a different thing from a building survey or a Home Report.
How Kanna Spatial does it
Kanna Spatial is a reality capture studio in Glasgow. We produce existing drawings from laser scans for architects, architectural technologists, designers and owners, with local pages for measured building surveys in Glasgow and Edinburgh. Drawings follow your CAD layer standard or Revit template, on sheets at 1:50 or 1:100 in DWG and PDF. Every drawing is checked before issue by a Chartered Architectural Technologist with ten years in architectural practice.
If you are the architect, the survey pack for architects adds a Revit model option, a 3D walkthrough and, where a flight is possible, drone photographs to the same set. For an example, see the West End townhouse case study. Every job is quoted at a fixed price before we attend, usually the same working day. Send us the address and what the drawings are for.
Questions
Can I use old drawings of the building?
Only if they still match the building. National guidance says the drawings in a planning application are cross-referenced with each other at validation. The proposals are drawn over the existing set, so an old set that no longer matches the building carries its errors into everything drawn from it.
Does listed building consent need drawings?
Yes. The law asks for a plan that identifies the building and such other plans and drawings as are necessary to describe the works. Our guide to measured surveys of listed buildings in Scotland covers what they need to show.
How much does a measured survey for planning cost?
A measured building survey is a set of accurate, scaled drawings of a building as it stands today: floor plans, elevations and sections, drawn from a laser scan or a 3D capture of the building and issued in DWG and PDF.