Airtightness testing in Scotland: who can test and what the rules say

In short

Under Scotland's April 2026 Technical Handbooks, an air test for a building warrant should be done by a tester registered with ATTMA or the Elmhurst Airtightness Scheme, or by a UKAS accredited body. New homes and most new non-domestic buildings are expected to be tested before completion, following CIBSE TM23. A building created by conversion needs no test.

By Connor Milton MCIAT, Chartered Architectural Technologist Published Last reviewed 5 minute read

Which buildings need an air test in Scotland?

New homes, and most new non-domestic buildings. The guidance is in Section 6 of the Scottish Government’s building standards technical handbooks, domestic and non-domestic. The current editions were published on 9 March 2026 and apply to building warrant applications made on or after 6 April 2026. Our page on building performance testing gives the short version of the routes below.

  • New homes. The domestic handbook says “all new homes should be tested”. Since 1 February 2023 each new-build dwelling is expected to be tested before completion, a move away from the sample testing used before.
  • New non-domestic buildings. The non-domestic handbook says new buildings and large extensions subject to standard 6.1 should be tested on completion. It lists two exceptions: a modular building under 150 m² that needs no site work beyond connecting the modules, where results exist for a similar configuration, and a building too large or complex to test in full, where the warrant submission shows this and sectional testing supports the declared infiltration rate.
  • Conversions. Both handbooks say there is no requirement to air test a new building created by conversion. They add that testing before and after the work can help with ventilation and indoor air quality.

Who can carry out an air test for a building warrant?

Normally, a tester whose competence is recognised through a registering organisation, or a UKAS accredited body. The handbooks say testing should only be carried out by people who can show relevant, recognised expertise in measuring the air permeability of buildings, and that this should include “membership of a professional organisation which accredits its members as competent to test and confirm the results of testing”.

The annexes explain how that competence is recognised: through registering organisations that apply the Minimum Technical Competency requirements and the National Occupational Standards for airtightness testing. Each organisation publishes a list of the people and firms registered with it and the categories of building each may test.

RouteWhat the handbooks say
Registered with ATTMANamed as a registration scheme
Registered with the Elmhurst Airtightness SchemeNamed as a registration scheme
A UKAS accredited bodyAn organisation that holds UKAS accreditation to ISO/IEC 17025:2017 for building air leakage tests as a site activity
Anyone elseThe verifier should accept the test only after satisfying itself, through documentary evidence, that the tester meets those requirements by other means. The handbooks expect this to be viable only in exceptional circumstances

The handbooks give the reason for that last line: the routes above include central lodgement of test data, quality sampling and independent verification of results if they are challenged.

How is the test done?

The handbooks say tests should follow CIBSE TM23, “Testing buildings for air leakage”. It describes two methods:

  1. Fan pressurisation (blower door). A fan pressurises or depressurises the building to 50 pascals. BS EN ISO 9972:2015 is the international standard for it, and ATTMA’s TSL1 to TSL3 give practical guidance.
  2. Low-pressure pulse. A measured pulse of air brings the building to 4 pascals, usually with at least two pulses. TM23 recognises it as a supplementary method, and no national or international standard exists for it yet.

The result is given as air permeability in m³/(h.m²) at 50 Pa. The domestic handbook says “no minimum value is set for uncontrolled infiltration”, but recommends designing for 7 m³/(h.m²) at 50 Pa or better, and asks a designer who specifies a higher rate to justify it to the verifier. Below 5, it says problems with indoor air quality and condensation may arise unless the ventilation strategy deals with them, commonly with continuous mechanical extract.

What should the test report show?

The handbooks list what the report should contain:

  • the tester’s contact details and their registration number with the relevant scheme
  • the building, and what was tested, with the state of the building at the time
  • the equipment used, with calibration details, and the test technique
  • the test data and the air permeability result, against the design figure declared in the building warrant
  • the date of the test

The results go to the verifier during the completion certificate process.

How can you check a tester or a certificate?

Each scheme lets anyone check online, on its own website:

  • ATTMA publishes a list of registered UK testers. The list also shows suspended testers, who ATTMA says are not currently authorised to test under its scheme. ATTMA certificates and reports raised after April 2022 carry a QR code: scan it, or type its 12 digit code into ATTMA’s Certificate and Report Validation page. ATTMA says a certificate or report without a QR code is not authentic.
  • The Elmhurst Airtightness Scheme has a Search for Tester by postcode, and a Validate Air Tester/Certificate page for checking that a tester is approved and validating a certificate. Elmhurst says it does not carry out tests itself, and that it took ownership of iATS on 1 June 2017.

What an air test cannot tell you

Where the air is leaking. The handbooks say an airtightness test quantifies the leakage but does not identify where it comes from. Combined with smoke visualisation or thermography it can help find the leakage paths, though this can be a complex task. Our guide to when to book a thermal imaging survey covers the conditions a thermal survey needs, and our guide to thermal imaging of tenements and sandstone buildings covers older solid walls.

This guide also cannot tell you how your verifier will treat a particular test. The verifier receives the results, and the handbooks leave the documentary evidence route to its judgement.

How Kanna Spatial does it

Kanna Spatial is a reality capture studio in Glasgow. In Scotland we carry out thermal imaging surveys to support retrofit and investigation work. They help find where the problem is. Passivhaus and EnerPHit certification, Energy Performance Certificates and BREEAM sign-off come from their own certifiers and assessors. For a building warrant test, check the tester on the ATTMA or Elmhurst register before you book.

If your project is a conversion or an extension, our guide to existing drawings for a building warrant covers the drawings councils expect. Every job is quoted at a fixed price before we attend, usually the same working day. Send us the address and what you want to find out.

Questions

Can a thermal imaging survey replace an air test?

Only in a narrow case. In remote areas or where severe weather makes testing impractical, the handbooks allow an alternative agreed in advance with the verifier: a thermography report by a registered thermographer, giving a qualitative indication of air permeability. The handbooks add that thermography may not accurately establish whether a building has been built to its design performance levels.

What happens if the building fails its air test?

The handbooks say a poor result shows the need for improvement and that specialist advice should be sought. Extra sealing must be durable and permanent, and they advise talking to the registered tester before remedial work so that it does not invalidate a later test. A result tighter than the design level may also need action, on ventilation.

Does a Passivhaus air test count for a building warrant?

Not if it follows ATTMA's TSL4. The handbooks say TSL4, which sets out the method for testing and reporting against the Passivhaus standard, is not suitable for building regulations compliance.

Sources

7
  1. Building standards technical handbook: domestic, April 2026 (clauses 6.2.4, 6.2.5 and Annex 6.D)Scottish Government. Read
  2. Building standards technical handbook: non-domestic, April 2026 (clause 6.2.6 and Annex 6.F)Scottish Government. Read
  3. Registered Air Tightness Testers: United KingdomATTMA. Read
  4. Certificate and Report ValidationATTMA. Read
  5. Elmhurst Airtightness SchemeElmhurst Energy Systems. Read
  6. Validate Air Tester/CertificateElmhurst Energy Systems. Read
  7. Join the Elmhurst Airtightness SchemeElmhurst Energy Systems. Read

Get a price

Get a fixed price, usually the same working day

Send the address and what you need. No call needed: we reply with a price and a survey date.

What happens next

  1. 01We reply with a fixed price, usually the same working day.
  2. 02We agree a survey date.
  3. 03You receive everything in your client portal.

Prefer email? studio@kannaspatial.co.uk

What do you need?
Get a fixed price Email